3.2 Migration/Cutover

Printer Friendly Page

3.2 Migration/Cutover

 

This activity involves the migration of a Palo Alto Networks Security Platform into production and the removal of the legacy firewall.

 

Part of the process will be for the Engineer to perform a Checklist which contains high-level items to improve successful delivery of Professional Services. The checklist has a list of minimum CLI and GUI steps to ensure a firewall placed in service is operational. A Post-Cutover Checklist will help ensure the firewall is operational and the Professional Services Engineer has communicated to the customer and Palo Alto Networks Consulting Services management the status of the new firewall.

 

Tasks include:

  • Complete Palo Alto Networks Pre-Cutover Task Checklist
  • Complete Pre-Cutover Customer Application Testing Benchmark Process
  • Migrate production traffic 
  • Perform Palo Alto Networks Post-Cutover Testing
  • Perform Post-cutover Customer Application Testing

 

Deliverables: 

  • Palo Alto Networks Pre-Cutover Task Checklist 
  • Pre-Cutover Customer Application Checklist
  • Palo Alto Networks Post-Cutover Test Checklist
  • Post-Cutover Customer Application Test Checklist

 

Consultant Collateral: 

  • Palo Alto Networks Pre-Cutover Task Checklist (Sample)
  • Pre-Cutover Customer Application Checklist (Sample)
  • Palo Alto Networks Post-Cutover Test Checklist (Sample)
  • Post-Cutover Customer Application Test Checklist (Sample)

 

 