Panorama Report Scheduling

L3 Networker

I created a group of reports that I want sent weekly via email and now I want to test sending them out to see what the look like and to make sure the data is right.

As far as I can tell I can only schedule with the GUI and the options are the days of the week.

How do I get a scheduled report to run now ? I can wait 24 hours between tests.

Thanks,
Justin

3 REPLIES 3

L3 Networker

I found this in the help. So it looks like its a non-configurable option. That's lame. I was thinking of tricking panorama into thinking its 2am. Thats a hack. If anyone has any ideas let me know and Thanks.

Use the Email scheduler to schedule reports for delivery by email. Before adding a schedule, you must define report groups and an email profile. Refer to Managing Report Groups and Configuring Email Notification Settings.

Scheduled reports begin running at 2:00 AM, and email forwarding occurs after all scheduled reports have finished running.

Justin

L4 Transporter

Did you try the Run Now button?

That works for individual reports. Not a group scheduled report. Unless I am missing something.

  • 1997 Views
  • 3 replies
  • 0 Likes
Like what you see?

Show your appreciation!

Click Like if a post is helpful to you or if you just want to show your support.

Click Accept as Solution to acknowledge that the answer to your question has been provided.

The button appears next to the replies on topics you’ve started. The member who gave the solution and all future visitors to this topic will appreciate it!

These simple actions take just seconds of your time, but go a long way in showing appreciation for community members and the LIVEcommunity as a whole!

The LIVEcommunity thanks you for your participation!